Morgan Lovell

Client: Bio Chemistry Society

Project Duration: 12 weeks

Brief Description of Works: 

  • To carry out the full design and installation of Mechanical Building Services at premises in Roger Street, London.
  • The first phase involved the removal of all of the existing building services and installation of new capital plant items, from the roof cold water storage tanks, the air conditioning & ventilation systems to the boilers, monoblock HWS and cold water booster system.
  • A total of 3 floors of offices were fitted out, including the entire toilet cores throughout the building (5 floors).
  • It was crucial that all systems installed were highly efficient & had to be registered on the ETL & compliant with the ECA http://www.eca.gov.uk/ . As such we carried out the installation of several floors of Daikin heat recovery VRVIII systems, heat reclaim ventilation units, Altherma HWS systems, pump and pressurisation room and a dedicated BMS controls package.